Road Projects Under Construction.

Road Projects Under Construction in Arizona DISTRICT NO. 1.
G. B. Shaffer, District Engineer.
F. D. Shufflebarger has contract 96% complete on the Wickenburg-Prescott N. R. M. 31 (1935), Phoenix-Prescott Highway. Joe de Arozena, resident engineer.
State forces have work of grading, draining and surfacing approximately 8.2 miles of road 20% complete on the Hope-Parker Highway, State Route 72, W.P.S.S. 112-C. Percy Jones, Sr., resident engineer.
Lee Moor Construction Co., has contract 86% complete for the oil processing by road mix method of 23.6 miles on the Ash Fork-Kingman Highway, extending northeast from Kingman, F.A.P. 80-G. C. S. Benson, resident engineer.
Skousen Brothers have contract 52% complete for grading, draining and placing aggregate base course on the Ashfork-Kingman Highway., U. S. 66. Work begins at the eastern boundary of Hualnai Indian Reservation, about 60 miles northeast of Kingman, and extends south asterly for 10.8 miles. F.A. 80-I. M. Kisselburg, resident engineer.
All Arizona Engineering and Construction Co. have contract 54% complete for grading, draining, placing aggregate base course on 1.8 miles on the Prescott-Jerome Highway, W.P.M.H. 12. 1. A. Quigley, resident engineer.
Tiffany Construction Co. have contract 86% complete for grading, draining and oiling of 14 miles on the Phoenix-Yuma Highway near Mohawk, F.A. 2nd Reo. W. T. Keplinger, resident engineer.
F. D. Shufflebarger has contract 88% complete to repair existing bridge and construct two additional spans over Sol's Wash at Wickenburg, Phoenix-Prescott Highway, A.F.E. 2402. Joe De Arozena, resident engineer.
Pearson & Dickerson have contract 50% completed for grading and draining 5.5 miles of roadway beginning about 22 miles N. E. of Prescott, F.A. 96-C, Prescott-Jerome Highway. J. A. Quigley, resident engineer.
Geo. W. Orr has been awarded a contract for the grading, draining and surfacing of 2.1 miles of highway 35 miles northeast of Kingman, Ashfork-Kingman Highway, W. P. G. H. 118-A. Percy Jones, Sr., resident engineer.
Phoenix-Tempe Stone Co. has been awarded a contract for grading, draining and oiling approaches to the Wickenburg Bridge, Phoenix-Prescott Highway, N. R. M. 59 and 84-C and N.R.H. 59. Joe De Arozena, resident engineer.
N. G. Hill Company has been awarded a contract for oiling 19 miles of highway beginning 30 miles northwest of Kingman and extending toward Boulder Dam Highway, W.P.S.S. 102.A and B. M. D. Glessner, resident engineer.
DISTRICT NO. 2
F. N. Grant, District Engineer R. C. Tanner & Co. has work 75% complete of grading, draining and placing select material on 8.5 miles of road way on the Flagstaff-Fredonia Highway, F.A.P. 95-H. The work begins at the Indian Reservation boundary, about 44 miles north of Flagstaff, and extends northerly to Cameron. H. B. Wright, resident engineer.
The Lee Moor Construction Co. have contract 34% complete for placing aggregate base course, shoulder material and cut-back plant mix on 18.2 miles of roadway on the Holbrook-Lupton Highway, F.A.P. 83-D. The work begins at Navajo-Apache County Line, about 21 miles northeast of Holbrook, and extends northeasterly. A. J. Kerr, resident engineer.
Ken Hodgman and Pearson & Dickerson have contract 92% completed for grading and draining roadway, and placing select material and aggregate base course on eleven miles of the Flagstaff-Fredonia Highway, F.A.P. 95-F. Work begins at north end of F.A.P. 95-B, about 92 miles north of Flagstaff, and extends northerly. J. M. Hobbs, resident engineer.
E. L. Yeager has contract complete for the removal and salvaging of old pavement, placing select material and paving with cement concrete three-tenths of a mile of paving within the city limits of Holbrook; Holbrook Streets, N.R.M. 40 (1934). A. J. Kerr, resident engineer.
E. L. Yeager has contract complete for the grading, draining and placing of select material, gravel sidewalk, curb and gutter and cut-back plant mix in the city of Winslow: Winslow Streets, F.A. 20 Reo, and 22 Reo. Oscar Maupin, resident engineer.
R. C. Tanner Co. has contract 65% complete to grade, drain and place dust palliative on 5.3 miles of the Holbrook-St. Johns Highway. F.A. 78-G. J. L. Bone, resident engineer.
Packard Construction Co. have been awarded a contract to grade, drain and place aggregate base course on 4.5 miles of the Showlow-Springerville Highway, W.P.H. 105-A. H. B. Wright, resident engineer.
Lee Moor Contracting Co. has awarded a contract 11% complete for the grading, draining and surfacing of 9.6 miles of the Holbrook-St. Johns Highway, W.P. H. 42. A. J. Kerr, Resident Engineer.
Ken Hodgman has been awarded a contract for grading, draining and dust palliative on 7.7 miles of highway, beginning 14.7 miles north of Flagstaff and extending towards Cameron, FlagstaffRedd, resident engineer.
Fredonia Highway, W.P.H. 95-J. Sam C.
R. C. Tanner Company has been awarded a contract for grading and draining 13.1 miles of highway between Ortega Lake and Concho, ShowlowConcho Highway, W.P.S.P. 104-А. Н. В. Wright, resident engineer.
Packard Contracting Company has been awarded a contract for grading, draining and placing aggregate base course on 10 miles of highway beginning 17 miles east of Showlow and extending easterly, Showlow-Springerville Highway, W.P.H. 105-L. H. B. Wright, resident engineer.
DISTRICT NO. 3
R. C. Perkins, District Engineer State forces have work of grading and draining approximately 3.1 miles on the Clifton-Springerville Highway, W.P.S.S. 101-D 93% complete. W. R. Stevens, resident engineer.
Lee Moor Contracting Co. has contract 54% complete for grading and draining approximately 4.7 miles of roadway on the Globe-Showlow Highway, F.A.P. 99-J. Work begins about 61 miles northeast of Globe and extends northeasterly. R. D. Canfield, resident engineer.
State forces have work 40% complete of grading, draining a section of road between Duncan and Clifton, W.P.S.S. 13-A, Duncan-Clifton Highway. W. R. Stevens, resident engineer.
State forces have work 75% complete bridge at Canyon Lake, N.R.S. 106-A. Apache Trail 94% complete. R. J. Holland, resident engineer.
W. E. Hall Co. has contract 46% complete to grade, drain and oil south on 17th Avenue to Greenhaw Street then to 19th Avenue on the Phoenix-Yuma Highway, W.P.M.H. 30-F. Geo. E. Lang, resident engineer.
Arizona Sand and Rock Co. have contract 85% complete for widening six miles of paving between Six Points and Glendale, Phoenix-Prescott Highway, W. P. M. H. 33. F. A. Berg, resident engineer.
Harry Hagen has contract 8% complete for grading and draining 3.2 miles of roadway near the Gila-Navajo County Line, F.A. 105-D, Globe-Springerville Highway, A.F. Rath, resident engineer.
Heuser and Garnett have contract 4% complete for the grading, draining and oiling of 8.8 miles between Coldwater and Buckeye, Phoenix-Yuma Highway, W.P.G.H., 46 B.&C. James A. Parker, resident engineer.
Daley Corporation has contract 65% complete to construct a concrete and steep underpass between Glendale and Peoria, Phoenix-Prescott Highway, W. P.G.H., 48. George E. Lang, resident engineer.
Tiffany Construction Co. has contract 3% complete for grading, draining and surfacing 2 miles of the Safford-Bowie Junction Highway, W.P.S.S. 115-B. N. G. Wallace, resident engineer.
State forces have work 95% complete on the grading and draining of 4.5 miles
ARIZONA HIGHWAYS
of roadway between Duncan and Clifton, N.R.S. 13-A. W. R. Stevens, resident engineer.
O. F. Fisher Construction Company has contract 90% complete for grading and draining approximately 6.4 miles of roadway about 50 miles northeast of Globe and extending northeasterly on the Globe-Showlow Highway, F.A. 99-H. R. D. Canfield, resident engineer.
DISTRICT NO. 4
W. R. Hutchins, District Engineer The Pleasant-Hasler Construction Co. have completed contract for the grading, draining, placing of aggregate base course and oil procedding by the plant-mix method of approximately 122/3 miles of the Ft. Hauchuca-Bisbee High-way, N.R.S. 108-A. A. J. Gilbert, resident engineer.
State forces have work of grading, draining and surfacing approximately three miles on the Nogales-Tombstone Highway, W.P.S.S. 109-C 99% complete. R. C. Bond, resident engineer.
White & Miller has completed contract for widening and resurfacing existing pavement on Tucson-Nogales Highway, F.A.P. 29 Reo. Work begins about 1.2 miles south of south city limits of Tucson and extends southerly approximately 1.5 miles. J. R. Van Horn, resident engineer.
State forces have work 99% complete of grading and draining a section of road between Nogales and Tombstone, W.P. S.S. 109-D. R. C. Bond, resident engi-neer.
Phoenix-Tempe Stone Co. have contract 57% complete to widen and resur-face existing pavement with cut-back plant mix, construct a cement rubble ma-sonry wall and a concrete culvert in the town of Lowell, F.A.P. 79-I, Sch. 1, Ben-son-Douglas Highway D. A. Flickenger, resident engineer.
J. A. Casson has contract 99% complete to grade, drain and place aggre-gate base course on highway beginning at Elfrida and extending north 10.2 miles, W.P.S.S. 114-C, Douglas-Safford Highway. H. Pinney, resident engineer.
Daley Corporation has completed contract to construct concrete overpass structure and approaches, including plant mix surfacing, about 12 miles west of Bisbee, W.P.G.S. 108-C. A. J. Gilbert, resident engineer.
Pleasant-Hasler Co. has contract 29% complete to grade, drain, place select material and plant mix on approximately 10.5 miles of roadway, beginning 12% miles south of the U. S. Military Reserv-ation and extending easterly. W.P.S.O. 108-B. A. J. Gilbert, resident engineer.
Borderland Construction Co. have contract 39% complete to grade, drain and oil 8.7 miles of the Ajo-Tucson Highway W.P.S.O. 110-C. Dan J. Lyons, resident engineer.
State forces have roadside improvement 62% complete on the Tombstone-Bisbee Highway, N.R.H. 79-G. D. A. Flickenger, resident engineer.
UNITED STATES DEPARTMENT OF AGRICULTURE BUREAU OF PUBLIC ROADS PROJECTS IN ARIZONA
G. L. McLane, Highway Engineer in Charge.
W. R. F. Wallace, Assoc. Highway Engineer, Supervising Engineer.
R. Thirion, Associate Highway Engineer, Highway Planning Engineer.
J. H. Brannan, Associate Highway Engineer, Supervising Engineer.
W. P. Wesch, Associate Highway Engineer, Locating Engineer.
W. J. Ward, Associate Highway Engineer, Locating Engineer.
E. F. Strickler, Assistant Highway Engineer, Supervising Engineer.
R. M. Rutledge, Assistant Highway Engineer, Office Engineer.
ROUTE 7-The Oak Creek National Forest Highway.
Bids for subgrade stabilization and crushed rock base course on sections G and H were opened in the Phoenix office of the Bureau of Public Roads on February 27, 1936. The Lee Moor Cntracting Company of El Paso, Texas, was low bidder.
The project begins at a point 12.7 miles south of Flagstaff, Arizona, and extends in a northerly direction to Flag-staff.
ROUTE 11-Payson-Colcord Mountain National Forest Highway.
The grading of Section C of this route, located about 30 miles east of Payson, is under contract to Bennett and Taylor. The length of the project is 4.218 miles. Work was shut down on December 31, 1935, because of severe winter weather and on that date project was 40% complete. G. E. Nelson, resident engineer.
Grand Canyon National Park Highways
The placing of a seal coat on Section H of Route 1, all of Route 10 and Sections A, B, C, D, and E of the Cameron-Desert View Approach to Grand Canyon National Park is under contract with Lee Moor Contracing Company. The length of the project is 32 miles. Work, when shut down on October 31, 1935, was about 42% complete. V. G. Watson, resident engineer.
Petrified Forest National Monument Highways
George W. Orr has contract for bituminous treated surfacing on Sections A,B1, and B2 of Route 1 and all of Route 2, Petrified Forest National Monument, Arizona. The length of the project is 25.3 miles. Work is approximately 20% complete. V. G. Watson, resident engineer.
ROUTE 3-Flagstaff-Clint's Well Na-tional Forest Highway.
The grading and drainage of Section C, 3.906 miles in length, beginning approximately 16 miles north of Clint's Well and extending toward Flagstaff, is under contract to Ernest W. Everly. Work was shut down on December 4, 1935, because of severe winter weather and on that date the project was 95% complete. F. A. Bonnell is resident engineer.
Surveys
Field work on the Verde River survey was started on January 30, 1936. The project begins at the south boundary of the Tonto National Forest, about 32 miles north of Phoenix, and will extend 51.5 miles to Forest Highway 9, the Fossil Creek Highway. G. E. Watson is chief in party.