Road Projects Under Construction in Arizona
Road Projects Under Construction in Arizona DISTRICT NO. 1.
G. B. Shaffer, District Engineer.
F. D. Shufflebarger has contract 96% complete on the Wickenburg-Prescott N. R. M. 31 (1935), Phoenix-Prescott Highway. Joe de Arozena, resident engineer.
State forces have work of grading, draining and surfacing approximately 8.2 miles of road 79% complete on the Hope-Parker Highway, State Route 72, W.P.S.S. 112-C. Percy Jones, Sr., resident engineer.
Lee Moor Construction Co., has completed contract for the oil processing by road mix method of 23.6 miles on the Ash Fork-Kingman Highway, extending northeast from Kingman, F.A.P. 80-G. C. S. Benson, resident engineer.
Skousen Brothers have contract 71% complete for grading, draining and placing aggregate base course on the Ashfork-Kingman Highway., U. S. 66. Work begins at the eastern boundary of Hualpai Indian Reservation, about 60 miles northeast of Kingman, and extends south easterly for 10.8 miles. F.A. 80-Ι. Μ. Kisselburg, resident engineer.
All Arizona Engineering and Construction Co. have contract 72% complete for grading, draining, placing aggregate base course on 1.8 miles on the Prescott-Jerome Highway, W.P.M.H. 12. J. A. Quigley, resident engineer.
Tiffany Construction Co. have completed contract for grading, draining and oiling of 14 miles on the Phoenix-Yuma Highway near Mohawk, F.A. 55 2nd Reo. W. T. Keplinger, resident engineer.
F. D. Shufflebarger has contract 93% complete to repair existing bridge and construct two additional spans over Sol's Wash at Wickenburg, Phoenix-Prescott Highway, A.F.E. 2402. Joe De Arozena, resident engineer.
Pearson & Dickerson have contract 75% completed for grading and draining 5.5 miles of roadway beginning about 22 miles N. E. of Prescott, F.A. 96-C, Prescott-Jerome Highway. J. A. Quigley, resident engineer.
Geo. W. Orr has contract 7% complete for the grading, draining and surfacing of 2.1 miles of highway 35 miles northeast of Kingman, Ashfork-Kingman Highway, W. P. G. H. 118-A. Percy Jones, Sr., resident engineer.
Phoenix-Tempe Stone Co. has contract 22% complete for grading, draining and oiling approaches to the Wickenburg Bridge, Phoenix-Prescott Highway, N. R. M. 59 and 84-C and N.R.H. 59. Joe De Arozena, resident engineer.
N. G. Hill Company has been awarded a contract for oiling 19 miles of highway beginning 30 miles northwest of Kingman and extending toward Boulder Dam Highway, W.P.S.S. 102.A-Band C. M. D. Glessner, resident engineer.
E. L. Yeager has been awarded a contract for the Oil Surfacing of 25.3 miles of roadway near the Boulder Dam on the
Kingman-Boulder Dam Highway, F.L.H. 2-A, B, C, D, & E. C. S. Benson, resident Engineer. DISTRICT NO. 2
F. N. Grant, District Engineer R. C. Tanner & Co. has work 89% complete of grading, draining and placing select material on 8.5 miles of roadway on the Flagstaff-Fredonia Highway, F.A.P. 95-H. The work begins at the Indian Reservation boundary, about 44 miles north of Flagstaff, and extends northerly to Cameron. H. B. Wright, resident engineer.
The Lee Moor Construction Co. have contract 35% complete for placing aggregate base course, shoulder material and cut-back plant mix on 18.2 miles of roadway on the Holbrook-Lupton Highway, F.A.P. 83-D. The work begins at Navajo-Apache County Line, about 21 miles northeast of Holbrook, and extends northeasterly. A. J. Kerr, resident engineer.
Ken Hodgman and Pearson & Dickerson have contract 92% completed for grading and draining roadway, and placing select material and aggregate base course on eleven miles of the FlagstaffFredonia Highway, F.A.P. 95-F. Work begins at north end of F.A.P. 95-B, about 92 miles north of Flagstaff, and extends northerly. J. M. Hobbs, resident engineer.
R. C. Tanner Co. has contract 65% complete to grade, drain and place dust palliative on 5.3 miles of the HolbrookSt. Johns Highway. F.A. 78-G. Oscar A. Manpin, resident engineer.
Packard Construction Co. have contract 2% complete to grade, drain and place aggregate base course on 4.5 miles of the Showlow-Springerville Highway, W.P.H. 105-A. H. B. Wright, resident engineer.
Lee Moor Contracting Co. has contract 18% complete for the grading, draining and surfacing of 9.6 miles of the Holbrook-St. Johns Highway, W.P. H. 42. A. J. Kerr, Resident Engineer.
Ken Hodgman has contract 10% complete for grading, draining and dust palliative on 7.7 miles of highway, beginning 14.7 miles north of Flagstaff and extending towards Cameron, Flagstaff-Fredonia Highway, W.P.H. 95-J. Sam C. Redd, resident engineer.
R. C. Tanner Company has contract 1% complete for grading and draining 13.1 miles of highway between Ortega Lake and Concho, Showlow-Concho Highway, W.P. S.O. 104-А. Н. В. Wright, resident engineer.
Packard Contracting Company has been awarded a contract for grading, draining and placing aggregate base course on 10 miles of highway beginning 17 miles east of Showlow and extending easterly, Showlow-Springerville Highway, W.P.H. 105-L. H. B. Wright, resident engineer.
Lee Moor Contracting Company has contract 1% complete for grading, draining and dust palliative on 3 miles of roadway about 38 miles southeast of Holbrook on the Holbrook-St. Johns Highway, W.P.H. 6-A. Oscar A. Maupin, resident engineer.
DISTRICT NO. 3
R. C. Perkins, District Engineer State forces have work of grading and draining approximately 4 miles on the Clifton-Springerville Highway, W.P.S.S. 101-E 5% complete. W. R. Stevens resident engineer.
Lee Moor Contracting Co. has contract 67% complete for grading and draining approximately 4.7 miles of roadway on the Globe-Showlow Highway, F.A.P. 99-J. Work begins about 61 miles northeast of Globe and extends northeasterly. R. D. Canfield, resident engineer.
State forces have completed bridge at Canyon Lake, N.R.S. 106-A. Apache Trail 94% complete. R. J. Holland, resident engineer.
State forces have work 75% complete bridge at Canyon Lake, N.R.S. 106-A. Apache Trail 94% complete. R. J. Holland, resident engineer.
W. E. Hall Co. has contract 98% complete to grade, drain and oil south on 17th Avenue to Greenhaw Street then to 19th Avenue on the Phoenix-Yuma Highway, W.P.M.H. 30-F. Geo. E. Lang, resident engineer.
Arizona Sand and Rock Co. have contract 99% complete for widening six miles of paving between Six Points and Glendale, Phoenix-Prescott Highway, W. P. M. H. 33. F. A. Berg, resident Harry Hagen has contract 28% complete for grading and draining 3.2 miles of roadway near the Gila-Navajo County Line, F.A. 105-D, Globe-Springerville Highway, A.F. Rath, resident engineer.
Heuser and Garnett have contract 22% complete for the grading, draining and oiling of 8.8 miles between Coldwater and Buckeye, Phoenix-Yuma Highway, W.P.G.H., 46 B.&C. James A. Parker, resident engineer.
Daley Corporation has contract 23% complete to construct a concrete and steep underpass between Glendale and Peoria, Phoenix-Prescott Highway, W. P.G.H., 48. George E. Lang, resident engineer.
Tiffany Construction Co. has contract 29% complete for grading, draining and surfacing 2 miles of the Safford-Bowie Junction Highway, W.P.S.S. 115-B. N. G. Wallace, resident engineer.
State forces have work 99% complete on the grading and draining of 4.5 miles of roadway between Duncan and Clifton, N.R.S. 13-A. W. R. Stevens resident engineer. O. F. Fisher Construction Company has contract 61% complete for grading and draining approximately 6.4 miles of