DECEMBER, 1936 ARIZONA HIGHWAYS 31 Road Projects Under Construction in Arizona DISTRICT NO. 1.

G. B. Shaffer, District Engineer.

Geo. W. Orr has contract 77% complete for the grading, draining and surfacing of 2.1 miles of highway 35 miles northeast of Kingman, Ashfork-Kingman Highway, W. P. G. H. 118-A. Percy Jones, Sr., resident engineer.

Pearson and Dickerson have contract 100% complete, W. P. M. H. 96-D, extending from Jerome to Clarkdale approximately 4 2-3 miles, and consisting of grading, draining and placing select material A. B. C. cut back plant mix. J. A. Quigley, resident engineer.

Phoenix-Tempe Stone Co. have contract 70% complete on the Wickenburg underpass, W. P. G. M. 98-1. The work is located in the town of Wickenburg and consists of the construction of a reinforced concrete underpass and approaches. Joe De Arozena, resident engineer.

State Forces are grading, draining and surfacing 1-2 mile of roadway on Prescott-Jerome Highway, A. F. E. 8968, Non-F. A., between Whipple Junction and U. S. 89. H. Pinney, resident engineer.

Geo. W. Orr has contract 30% complete for grading, draining and placing Aggregate Base Course on 5½ miles of the Prescott-Jerome Highway, F. A. 96-C, beginning at the National Forest Boundary and extending toward Jerome. H. Pinney, resident engineer.

Geo W. Orr has contract 35% complete for grading, draining and placing base course material on 1.7 miles of the Ashfork-Kingman Highway, F. A. 118-B, beginning at the southwest end of N. R. H. 80-J and extending southwesterly. Percy Jones, Sr., resident engineer.

E. L. Yeager has contract 100% complete for the oil surfacing of 25.3 miles of the Kingman-Boulder Dam Highway, F.L.H. 2-A, B, C, D and E, near the Boulder Dam. C. S. Benson, resident engineer.

Phoenix Tempe Stone Company has contract 13% complete for grading, draining, placing Aggregate Base Course and oiling 0.4 mile of roadway immediately west of the Wickenburg Underpass, F. A. 98-I (1937), Blythe-Wickenburg Highway. Joe DeArozena, resident engineer.

Tanner Construction Company has been awarded a contract for the grading, draining, placing of Aggregate Base Course and Oiling 1.9 miles of roadway south of Wickenburg, F. A. 52-2nd Reo. (1937), Wickenburg - Morristown Highway. Joe DeArozena, resident engineer.

Pearson and Dickerson have contract 11% complete for the placing of Aggregate Base Course and Oil on approximately 6 miles of roadway between Jerome and Clarkdale on the Prescott-Flagstaff Highway, F. A. 12 Reo (1937) and F. A. 17 Reo (1937). J. A. Quigley, resident engineer.

State Force have roadwide improvement 94% complete on Prescott-Jerome Highway, F.A. 36. H. Pinney, resident engineer.

State Forces are laying Dust Palliative on 17.1 miles of roadway between Bouse and Parker, Hope-Parker Highway, A.F.E. 7201. D. L. Henderson, foreman.

DISTRICT NO. 2.

F. N. Grant, District Engineer.

Packard Contracting Company has contract 98% complete for grading, draining and placing aggregate base course on 10 miles of highway beginning 17 miles east of Showlow and extending easterly, Showlow-Springerville Highway, W.P.H. 105-В. Н. В. Wright, resident engineer.

O. F. Fisher has contract 69% complete to grade, drain and place aggregate base course on 15.5 miles of roadway on the Showlow-Springerville Highway, W.P.H. 105-C. J. M. Hobbs, resident engineer.

Tanner Construction Co. has contract 99% complete for the construction of a reinforced concrete subway at Winslow on the Winslow-Pine Highway, W.P.G.M. 107. A. J. Kerr, resident engineer.

State Forces have roadside improvement 90% complete on Flagstaff, Williams Highway, W.P.M.H. 24-A. Oscar Maupin, resident engineer.

Ken Hodgman has contract 43% complete for the grading, draining and placing of base course on 5½ miles of the Flagstaff-Fredonia Highway, F.A. 95-J, beginning 22½ miles northeast of Flagstaff and extending toward Cameron. Oscar A. Maupin, resident engineer.

State Forces are 45% complete on Roadside Improvement work between Williams and Flagstaff on the Ashfork-Flagstaff Highway, F. A. 89-E, R. I. Oscar A Maupin, resident engineer.

W. E. Hall Company has contract 18% complete for placing Aggregate Base Course and Oiling 8.5 miles of roadway south of Cameron, F. Α. 95-Η (1937), Flagstaff-Fredonia Highway. Sam C. Redd, resident engineer.

W. E. Hall Company has contract 18% complete for grading and draining 4 miles of roadway between Showlow and Navajo County Line, F. A. 105-Η (1937), Globe-Springerville Highway. H. B. Wright, resident engineer.

State Forces have roadside improvement work 85% complete on Ashfork-Flagstaff Highway, W.P.H. 89-D. Oscar Maupin, resident engineer.

State Forces have roadside improvement work 85% complete on Ashfork-Flagstaff Highway W.P.H. 89-F. Oscar Maupin, resident engineer.

DISTRICT NO. 3.

R. C. Perkins, District Engineer.

Lee Moor Contracting Co. have contract 92% complete, F.A. 105-F and F. L. H. 6-A, Unit 3, beginning 7 miles N. E. of Navajo county line about 70 miles N. E. of Globe and extending northeasterly approximately 10.8 miles, work consisting of grading and draining roadway. A. F. Rath, resident engineer.

Tiffany Construction Company have contract 97% complete for the grading and draining of 3.9 miles of the Mesa Superior Highway, A.F.E. 8077, Non-F. A., near Florence Junction. Frank A. Berg, resident engineer.

State Forces have the LaBarge Creek Bridge 90% complete on the Apache Trail, A.F.E. 8801, Non-F. A. R. J. Holland, resident engineer.

Pleasant Hasler has contract 17% complete for construction of arch design bridges over Cedar Canyon and Corduroy Creek on Globe-Springerville Highway, F.A. 105-E, about 70 miles northeast of Globe. F. A. Rath, resident engineer.

Lee Moor Contracting Company has contract 100% complete for grading and draining 2 miles of the Globe-Showlow Highway, F. A. 105-G, beginning about 17.7 miles northeast of the Navajo county line and extending northeasterly. A. F. Rath, resident engineer.

Arizona Sand & Rock Company has contract 29% complete for the widening of pavement between 15th and 17th Avenues on Van Buren Street, and between Van Buren and Jefferson Streets on 17th Avenue, Phoenix-Yuma High-

ARIZONA HIGHWAYS

way, F.A. 30-E. Geo. E. Lang, resident W.P.G.M. 79-H. A. J. Gilbert, resident Route 3, Flagstaff-Clints Well National engineer. engineer. Forest Highway Arizona Sand and Rock Company has Tanner Construction Co. has contract The grading and drainage of Section contract 15% complete for widening 50% complete for the construction of a D, 4.280 miles in length, beginning ap pavement between Six Points and Glenconcrete and steel overpass structure proximately 20 miles north of Clints dale and between Glendale and Peoria, and approaches, Tombstone Nogales Well and extending toward Flagstaff, is a total of 4.35 miles, F. A. 33-Reo (1937), Highway, W.P.G.S. 49, at Fairbanks. D. under contract to Ernest W. Everly, Al Phoenix-Glendale Highway and F. A. A. Flickinger, resident engineer. buquerque, New Mexico. Work is ap 48-A Reo. (1937), Phoenix Prescott proximately 75% complete. F. A. Bonnell, Highway. R. D. Canfield, resident engiresident engineer. neer.

W. E. Hall Company has contract 72% State Forces have Roadside ImproveRoute 11, Payson-Colcord Mountain complete for placing Select Material ment 75% complete on Mesa Ruins National Forest Highway and Oiling 1.6 miles of of roadway between Highway, F. A. 97-B. R. C. Bond, resi Tempe and Scottsdale, W.P.S.O. Tempedent engineer. The grading and installation of drain Scottsdale Highway. Jas. A. Parker, resiage structures on Section D and the plac dent engineer. ing of disintegrated granite on Sections B. C. and D of this route are under con tract to All Arizona Engineering and Construction Company. Work is about 98% complete. G. E. Nelson, resident en gineer.

Vinson and Pringle have contract 3% State Forces are grading, draining and complete to construct a concrete and surfacing 3.5 miles of roadway between steel overpass and earthwork approach Pima County Line and Oracle Junction, on McClintock Avenue, 1 mile east and A. F. E. 8016, Tucson-Florence Highway, 4 mile south of Tempe, W.P.G.S. 126, Dan J. Lyons, resident engineer. Tempe-Chandler Highway. Geo. E. Lang, resident engineer.

State Forces are doing Roadside ImRoute 19, Clifton-Alpine National provement work between Picacho and Forest Highway Red Rock, F. A. 94-C, R. I., Florence Tucson Highway. R. C. Bond, resident enH. J. Hagen has contract for grading gineer. and installation of drainage structures on a portion of Section B of this route. Length of project is 1.854 miles. Work is about 80% complete. C. H. Clark, resi dent engineer.

Harry Hagen has contract 10% comJ. A. Casson has been awarded a con plete for bridge construction on the Globetract for the grading, draining and plac Springville Highway, A.F.E. 6059, Noning of cutback plant mix on 1.5 miles of Federal Aid. A. F. Rath, resident enroadway near Douglas on the Benson gineer. Douglas Highway, F.A. 79-J, Schedule 3 (1937). A. J. Gilbert, resident engineer.

DISTRICT NO. 4. Route 30, Globe-Showlow National Forest Highway William R. Hutchins, District Engineer. UNITED STATES DEPARTMENT OF AGRICULTURE Lee Moor Contracting Company has Packard Contracting Company, Phoe contract 100% complete to construct a BUREAU OF PUBLIC ROADS nix, Arizona, has contract for construc reinforced concrete overpass and aption of a bridge across Showlow Creek on proaches at Cochise on the Douglas-SafG. L. McLane, Senior Highway EnSection B. of Arizona Forest Highway ford Highway, W.P.G.S. 114-D. Gene gineer in Charge. Route 30, Globe-Showlow, and grading Gilpin, resident engineer. and placing subgrade reinforcement on Section C of the same route. Work is about 30% complete. V. G. Watson, resi dent engineer.

Arizona Sand and Rock Company has W. R. F. Wallace, Highway Engineer, contract 100% complete for the grading, Supervising Engineer. draining and oiling of 14.4 miles of roadway between Casa Grande and Sacaton R. Thirion, Associate Highway Engineer, Highway Planning Engineer. W.P.M.S. & W.P.S.S. 122. R. C. Bond, resident engineer. J. H. Brannan, Associate Highway Engineer, Supervising Engineer. J. A. Casson has contract 100% comW. P. Wesch, Associate Highway plete for the construction of a concrete Bridge Engineer, Bridge Engineer. and steel structure underpass at Douglas, on the Benson-Douglas Highway, W. J. Ward, Associate Highway Engineer, Locating Engineer.

E. F. Strickler, Assistant Highway Engineer, Supervising Engineer.

R. M. Rutledge, Assistant Highway Engineer, Office Engineer.