PROJECTS UNDER CONSTRUCTION
Road Projects Under Construction in Arizona DISTRICT NO. 1
G. B. Shaffer, District Engineer Geo. W. Orr has contract 96% complete for the grading, draining and surfacing of 2.1 miles of highway 35 miles northeast of Kingman, Ashfork-Kingman Highway, W. P. G. H. 118-А. С. В. Browning, resident engineer.
Geo. W. Orr has contract 92% complete for grading, draining and placing base course material on 1.7 miles of the Ashfork-Kingman Highway, F. A. 118-B, beginning at the southwest end of N. R. H. 80-J and extending southwesterly. C. B. Browning, resident engineer.
Phoenix-Tempe Stone Co. have contract 93% complete on the Wickenburg underpass, W. P. G. M. 98-1. The work is located in the town of Wickenburg and consists of the construction of a reinforced concrete underpass and approaches. Joe De Arozena, resident engineer.
Phoenix-Tempe Stone Company has contract 94% complete for grading, draining, placing Aggregate Base Course and oiling 0.4 mile of roadway immediately west of the Wickenburg Underpass, F. A. 98-1 (1937), Blythe-Wickenburg Highway. Joe De Arozena, resident engineer.
Tanner Construction Company has contract 66% complete for the grading, draining, placing of Aggregate Base Course and Oiling 1.9 miles of roadway south of Wickenburg, F. A. 59-2nd Reo. (1937), Wickenburg Morristown Highway. Joe DeArozena, resident engineer.
State Forces have completed the grading, draining and surfacing 1-2 miles of roadway on Prescott-Jerome Highway, A. F. E. 8968, Non-F. A., between Whipple Junction and U. S. 89. H. Pinney, resident engineer.
Geo. W. Orr has contract 95% complete for grading, draining and placing Aggregate Base Course on 5 1-2 miles of the Prescott-Jerome Highway, F. A. 96-C, beginning at the National Forest Boundary and extending toward Jerome. H. Pinney, resident engineer.
State Forces have roadside improvement 94% complete on Prescott-Jerome Highway, F. A. 36. (Temporarily suspended on account of weather). H. Pinnev, resident engineer.
Pearson and Dickerson have contract 56% complete for the placing of Aggregate Base Course and Oil on approximately 6 miles of roadway near Jerome on the Prescott-Jerome Highway, F. A. 12 Reo (1937) and F. A. 17 Reo (1937). J. A. Quigley, resident engineer.
N. G. Hill Company has contract 46% complete for the widening and resurfacing of one and two-thirds miles of roadway near Stoval on the Yuma-Phoenix Highway, F. A. P. 55-3rd Reopening (1937). M. Kisselburg, resident engineer.
Lee Moor Contracting Company has contract 17% complete for the grading, draining, placing Aggregate Base Course and Asphaltic Surface Treatment on about 10 miles of roadway beginning about 16 miles northwest of Kingman and extending northeasterly, on the Kingman-Boulder Dam Highway, F.A.P.
123 (1937). C. S. Benson, resident engineer.
N. G. Hill Company has contract 15% complete to grade, drain, place Aggregate Base Course and Asphaltic Surface Treatment on 7.3 miles of roadway, beginning at Maricopa County Line, extending northerly. Gila-Bend-Ajo Highway, W. P. S. S. 120. M. Kisselburg, resident engineer.
Tanner Construction Company has contract 74% complete for replacing a ford with new six span concrete box culvert and reconstructing approaches at Aztec on Phoenix-Yuma Highway, F. A. 55-3rd Reo., Schedule 2. M. Kisselburg, resident engineer.
DISTRICT NO. 2
F. N. Grant, District Engineer.
Packard Construction Company has contract 99% complete for grading, draining and placing Aggregate Base Course on 10 miles of highway beginning 17 miles east of Showlow and extending easterly, Showlow-Springerville Highway, W. P. H. 105-B. (Temporarily suspended on account of weather). H. B. Wright, resident engineer.
W. E. Hall Company has contract 65% complete for grading and draining 4 miles of roadway between Showlow and Navajo County Line, F. A. 105-H. (1937), Globe-Springerville Highway. (Temporarily suspended on account of weather). H. B. Wright, resident engineer.
Phoenix Tempe Stone Company has contract 2% complete for the construction of a steel arch bridge over Canyon Padre, 24 miles east of Flagstaff, and new road mix oil surface approaches forming a line change of about one mile on the Winslow-Flagstaff Highway, F. A. P. 81-2nd Reopening (1937), F. A. Berg, resident engineer.
O. F. Fisher has contract 94% complete to grade, drain and place Aggregate Base Course on 15.5 miles of roadway on the Showlow-Springerville Highway, W.P.H. 105-C. J. M. Hobbs, resident engineer.
Ken Hodgman has contract 100% complete for the grading, draining and placing of Base Course on 5 1-2 miles of the Flagstaff-Fredonia Highway, F. A. 95-J, beginning 22 1-2 miles northeast of Flagstaff and extending toward Cameron. Oscar A. Maupin, resident engineer.
State Forces and W. P. A. have grading and draining of 3 miles of roadway from Winslow underpass to connect with Winslow-Pine Highway 32% complete. Also 8% complete and construction of multi-span concrete box culvert over dip 2 miles West of Winslow. Canyon PardeHolbrook-Sunset Pass Highway, A. F. E. 5102. F. A. Berg, resident engineer.
State Forces and W. P. A. are constructing curb, gutter and sidewalk in town of St. Johns on Holbrook-Springer ville Highway, A. F. E. 5301 Β. Α. Willmoth, transitman in charge.
DISTRICT NO. 3
R. C. Perkins, District Engineer.
Pleasant-Hasler has contract 21% complete for construction of arch de-sign bridges over Cedar Canyon and Corduroy Creek on Globe-Springerville Highway, F. A. 105-E., about 70 miles northeast of Globe. F. A. Rath, resident engineer.
Harry Hagen has contract 38% complete for bridge construction on the Globe-Springerville Highway, A. F. E. 6059, Non-Federal Aid. A. F. Rath, resident engineer.
Arizona Sand and Rock Company has contract 83% complete for the widening of pavement between 15th and 17th Avenues on Van Buren Street, and between Van Buren and Jefferson Streets on 17th Avenue, Phoenix-Yuma Highway, F. A. 30-E. Geo. E. Lang, resident engineer.
Vinson and Pringle have contract 83% complete to construct a concrete and steel overpass and earthwork approach on McClintock Avenue, 1 mile east and 1-4 mile south of Tempe, W.P.G.S. 126, Tempe-Chandler Highway. Geo. E. Lang, resident engineer.
Arizona Sand and Rock Company has contract 99% complete for widening of pavement between Six Points and Glendale and between Glendale and Peoria, a total of 4.35 miles, F. A. 33-Reo (1937), Phoenix-Glendale Highway and F. A. 48-A Reo. (1937), Phoenix Prescott Highway. R. D. Canfield, resident engineer.
Tiffany Construction Company has contract 35% complete to place Aggregate Base Course and Oil 8.9 miles of roadway near Florence Junction. Mesa-Superior Highway, F. A. 7-2nd Reo (1937). A. J. Kerr, resident engineer.
Pearson & Dickerson have contract 10% complete for widening 3.5 miles of pavement on Tempe-Mesa Highway, F. A. 8-A, 2nd Reo (1937). Jas A. Parker, resident engineer.
State Forces and W. P. A. are widening roadway and structures from Clifton to Metcalf on Clifton-Springerville Highway. A. F. E. 3701. Raymond Gardner, resident engineer.
State Forces and W. P. A. are constructing sidewalks and widening concrete pavement from 24th Street (Phoenix) to Tempe Bridge on East Van Buren Street. Phoenix-Tempe Highway, A. F. E. 2103. R. J. Holland, resident engineer.
State Forces have Roadside Improvement 61% complete on Florence-Tucson Highway, F. A. 94-B, 1st Reopening. Mark H. Layn, resident engineer.
DISTRICT NO. 4
William R. Hutchins, District Engineer Phoenix-Tempe Stone Company has contract 44% complete for the resurfacing and widening of about one-third mile of existing pavement with Cutback Asphaltic Plant Mix within the City Limits of Bisbee, Benson-Douglas Highway, F. A. P. 11-B (1937). A. J. Gilbert, resident engineer.
State Forces have completed grading draining and surfacing 3.5 miles of roadway between Pima County Line and Oracle Junction, A. F. E. 8016, Tucson-Florence Highway. Dan J. Lyons, resident engineer.
ARIZONA HIGHWAYS
J. A. Casson has contract 76% complete for the grading, draining and placing of cutback plant mix on 1.5 miles of roadway near Douglas on the Benson-Douglas Highway, F. A. 79-J, Schedule 3 (1937). Α. J. Gilbert, resident engi-neer.
State Forces and W. P. A. have work 14% complete on grading and draining 10 miles of roadway on Nogales-Patagonia Highway, A. F. E. 8213. R. C. Bond, resident. engineer.
State Forces and W. P. A. are 27% complete on construction of curb, gutter and sidewalk and grading, draining and oil surfacing approximately 1.5 miles of roadway (one-half of which is within Nogales City Limits) on Nogales-Pata-gonia Highway, A. F. E. 4502. R. C. Bond, resident engineer.
State Forces and W. P. A. are constructing curb, gutter, sidewalks and widening pavement from Government Hospital to County Fair Grounds on U. S. 89 south of Tucson. Tucson-Nogales Highway, A. F. E. 4101. D. J. Lyons, resident engineer.
State Forces and W. P. A. are widening roadway and structures on Casa Grande-Picacho Highway, A. F. E. 2701. Mark H. Layn, resident engineer.
State forces and W. P. A. are constructing approximately 20 miles of stock fence and cattle guards on State Route 84 Picacho-Tucson Highway. A. F.. E. 4102. Mark H. Layn, resident engineer.
State Forces and W. P. A. are widening roadway and structures on Bisbee-Douglas Highway A. F. E. 4401. Boone Waughtal, engineer in charge.
State Forces have started Roadside Improvement work between Duncan and New Mexico State Line, Safford-State Line Highway, F. A. 88-Ć. W. P. Wachs, foreman.
UNITED STATES DEPARTMENT OF AGRICULTURE BUREAU OF PUBLIC ROADS
New Post Office Building Phoenix, Arizona April 1, 1937 G. L. McLane, Senior Highway Engineer in Charge.
W. R. F. Wallace, Highway Engineer, Supervising Engineer.
R. Thirion, Associate Highway Engineer, Highway Planning Engineer.
J. H. Brannan, Associate Highway Engineer, Supervising Engineer.
W. P. Wesch, Highway Bridge Engineer, Bridge Engineer.
W. J. Ward, Associate Highway Engineer, Locating Engineer.
E. F. Strickler, Associate Highway Engineer, Supervising Engineer.
R. M. Ruthledge, Assistant Highway Engineer, Office Engineer.
BUREAU OF PUBLIC ROADS PROJECTS IN ARIZONA UNDER CONSTRUCTION Route 7, Oak Creek National Forest Highway
The grading of Section K of this route is under contract to Lee Moor Contracting Company. Length of project 1.872 miles. Work is about 75% complete. C. R. Brashears, resident Engineer.
Route 19, Clifton-Alpine National Forest Highway
H. J. Hagen has contract for grading and installation of drainage structures on a portion of Section B of this route. Length of project is 1.854 miles. Work is about 80% complete. C. H. Clark, resident engineer.
Route 30, Globe-Showlow National Forest Highway
Packard Contracting Company, Phoenix, Arizona, has contract for construc-tion of a bridge across Showlow Creek on Section B of Arizona Forest Highway Route 30, Globe-Showlow, and grading and placing subgrade reinforcement on Section C of the same route. Work is about 98% complete. V. G. Watson, resident engineer.
California-Arizona Federal Lands Route 8
Wickes Engineering and Construction Company, Des Moines, Iowa, has contract for construction of Parker Bridge and approaches. Length of project 0.84 miles. W. K. Bertken, resident engineer.
National Park Projects:
J. A. Casson, Phoenix, Arizona, has contract for placing bituminous treated surfacing on Grand Canyon Route 8. Length of project 8.639 miles. Work will be started when weather conditions permit. V. G. Watson, resident engineer.
G. Clay Gates, Thermopolis, Wyoming, has contract for installation of 17,000 feet of metal plate guard rail on the Cameron-Desert View Approach to Grand Canyon National Park. Length of project 28 miles. Work has not yet been started.
Skousen Brothers, Albuquerque, New Mexico, has contract for grading, base course, and light surface application of oil on a portion of Grand Canyon Route 4 and Sections C, D, E, and F of the Jacobs Lake Approach to the North Rim. Length of project 31.93 miles. On account of snow, work will not be started until about May 1st.
BIDS TO BE OPENED
Bids will be received until 10:00 a. m. April 13, 1937, at the Phoenix Office, Bureau of Public Roads, for grading and placing subgrade reinforcement of Section C of Route 1, Petrified Forest National Monument. Length of project 4.84 miles.
The Unique Magazine Of the Inland Empire Arizona Highways
$1.00 Per Year A complete unit of the petroleum Industry-ProducersRefiners- -Marketers.
Rio Grande Petroleum Products are available through out the Southwest.
ARIZONA HIGHWAYS
STOP AND GO DRIVING IS COSTLY
Every time you start up from a normal traffic stop, you can waste enough gasoline to drive a third of a mile!
To cut down the high cost of today's stop-and-go driving in village, town, and city, Shell engineers developed a way to "balance" gasoline.
This balancing process re-arranges the entire chemical structure of gasoline - makes it "digestible" for your engine -just as cooking makes food digestible for you.
Your motor gets the full benefit of Super-Shell's high energy content.
Super-Shell-the "MOTORDIGESTIBLE" gasoline is sold from coast to coast.
There's a Shell station in your neighborhood. Stop there "next time."
Round town
4 out of every 5 miles you drive are STOP and GO
SUPER SHELL
Already a member? Login ».