Projects Under Construction In Arizona

District No. 1, Geo. B. Shaffer, District Engineer Schmidt & Hitchcock have completed the oil surfacing of F. A. 55 Reo. beginning at Wellton and extending east 42½ miles. George Lang, Resident Engr.

Lee Moore Contracting Co. has completed the concrete dip four miles north of Gila Bend. F. A. P. 53-1 Reo., A. W. Newhall, Res. Engr.

M. H. Slocum has the grading, draining and gravel surfacing of 7.4 miles F.A. 80 D., (beginning at Seligman and extending west) 80% complete, Floyd J. Beeghly Res. Engr.

Canion, Francis & Royden has the grading, draining and gravel surfacing of 5.6 miles of the Phoenix-Yuma Highway (beginning at Ligurta and extending east) completed, James A. Parker, Res. Engr.

Skeels and Graham have the grading, draining and oil processing and construction of fifteen miles of road including two concrete bridges (beginning at Gila Bend and extending west), F. A. Reo., completed, A. W. Newhall, Res. Engr.

Gribble & Burke have the construction on oiling approximately 17 miles of the Topock-Oatman Highway 77% complete. H. O. Norville, Res. Engr.

The Western Gunite Co. has the contract for the oil surfacing of eight miles F.A. 26-D Reo. (beginning at Ligurta overpass and extending east), 50% complete, Geo. E. Lang, Res. Engr.

Yglesias Brothers have the construction of placing subgrade stabilizer on 9.3 miles of Ashfork-Seligman Highway (beginning at Pinevita and extending west), F. A. 57 Reo., 90% complete, Floyd J. Beeghly, Res. Engr.

H. L. Royden has the construction of two bridges and widening fill and placing subgrade stabilizer, F.A. 55 Reo. (beginning ½ mile north of Stovall), 87% complete, Jas. H. Parker, Res. Engr.

Martter & Bock have the construction contract for the grading and draining of 4.5 miles (beginning 2 miles east of Hackberry and extending west) on F. A. Project 80-E 1% complete. H. O. Norville, Res. Engr.

District No. 2, F. N. Grant, Dist. Engr.

Ben Pearce Construction Co. has the gravel surfacing of 22½ miles of U. S. 66 (beginning at Sanders and extending to the New Mexico state line), 68% complete, H. Pinney, Res. Engr.

Veater and Davis have the construction of 49 miles from Cameron to the Ridge Trading Post on U. S. 89 (F.A. 95-B) 8% complete, H. D. Alexander, Res. Engr.

McGinty Construction company has been awarded a contract for the construction of S. 20 & Non 40-C, Schedule No. 2 in the city of Winslow, J. P. Flynn, Res. Engr.

H. L. Royden has been awarded a contract for the construction of 5½ miles, beginning at Holbrook and extending east on Route 70, F. A. Project No. 78F. J. P. Flynn, resident engineer.

District No. 3, R. C. Perkins, Dist. Engr.

R. H. Martin has been awarded the contract for the construction of the approaches to the Tempe bridge, F. A. No. 2-B. Gus Rath, resident engineer.

Lynch-Canon Engineering Co. has the construction of the Tempe Bridge 80% complete, A. F. Rath, Res. Engr.

Martin Bros. have construction of the oil processing of 30½ miles of the Globe-Safford highway (beginning at Coolidge Dam and extending east), 28% complete, A. 87-B, M. Kisselburg, Res. Engr.

Lee Moore Contracting Co. has contract for the grade, drain and sub-grade surfacing of five miles of U. S. 180, (beginning at Geronimo and extending west, F. A. 15-D., 45% complete, L. C. Bolles, Res. Engr.

Lee Moore Contracting Co. has construction on F. A. Project 88-C, (beginning at Duncan and extending to the state line), 48% complete, H. B. Wright, Res. Engr.

Robert E. McKee has the grading and draining of 13.7 miles of U. S. 180, F. A. 87-E. (beginning at Geronimo and extending east), 4% complete, L. C. Bolles, Res. Engr.

Skeels & Graham have been awarded a contract for the surfacing and oiling of 11.6 miles (beginning at Duncan and extending west) on F.A. Project 88-B Reo., Daniel Thompson. Res. Engr.

Skeels & Graham have the surfacing and oiling of 8 miles (beginning at the east end of the pavement and extending east) F. A. Project 88-A Reo., 30% complete, Daniel Thompson, res. engr.

Stanley Jaicks Co. has the construction of the Florence paving 56% complete, Joe de Arozena, Res. Engr.

SEE ARIZONA FIRST For Your Vacation

See Us First For Your Office Supplies H. M. CLARK OFFICE SUPPLY CO. 123 N. 2nd Ave. Phoenix

PHOENIX BLUE PRINT CO. PHOENIX, ARIZONA

Tycos Thermometers Hamilton Drawing Boards Drafting Room Equipment Photostat Printing Drawing Material Blue Printers Surveying Instruments Measuring Tapes

WRICO LETTERING GUIDES

CITY, COUNTY AND STATE MAPS U. S. G. S. TOPOGRAPHIC MAPS HOME BUILDERS' BLDG.

128 N. First Ave.

Phone 4-2407

Tools--General Hardware Heavy Hardware and Supplies Large Wholesale Stocks Momsen - Dunnegan - Ryan Co.

Phoenix, Arizona